FOOTPATH NO. 60 CHURCH LANE TO LONG CAUSEWAY, ACROSS BEDQUILTS

Re the ongoing weather problems that have led to the footpath works from Church Lane to Bedquilts being delayed. See latest update.

“We now have a firm start date from KBI UK for the agreed resurfacing works to The Lane/Footpath No. 60. 

This will be starting on Monday 21 May for the ground-workers to come in and do the preliminary crushed stone levelling, filling and re-grading work for 3-4 days. 

Then on Friday 25th KBI will bring in the Flexi-pave materials for storage on site ready to start on the Flexi-pave laying by hand on Monday 28 May for a further 3-4 days.”